Substation / point of interconnection · Hill County
Tap 345kV 68090 Sam Switch – 3389 Fort Smith
1 active project totalling 201 MW is queued to connect at Tap 345kV 68090 Sam Switch – 3389 Fort Smith in Hill County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0166 | Compadre Solar II | Solar | 201 | Sync Approved | 12/31/2026 | 1 |