24INR0407 · Solar · Hill County
Mercury Solar III
Mercury Solar III is a 204 MW solar project in Hill County, Texas, connecting at 68092 Liberty Station 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0407
- Capacity
- 204 MW
- Fuel
- Solar (PV)
- Substation
- 68092 Liberty Station 345kV
- County
- Hill County
- Interconnecting entity
- Mercury Solar
- Projected COD
- 04/01/2029
- Entered queue
- 08/03/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/12/2025FIS Requested → IA Signed
- 08/03/2022Entered the queue with 204 MW, projected COD 04/01/2029
- 08/03/2022Screening → FIS Requested
Other projects at this substation
| Mercury Storage SLF | BESS | 0 MW | FIS Requested |