ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0023 · Solar · Hill County

Compadre Solar

COD delayed 1×

Compadre Solar is a 406 MW solar project in Hill County, Texas, connecting at tap 345kV 68090 Sam Switch - 1907 Venus. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/31/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0023
Capacity
406 MW
Fuel
Solar (PV)
Interconnecting entity
Hill Solar I, LLC
Projected COD
10/31/2026
Entered queue
03/08/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 07/31/2026 → 10/31/2026 (+3 months)
  • 11/13/2024
    Energization Approved → Sync Approved
  • 10/30/2024
    IA Signed → Energization Approved
  • 01/31/2024
    FIS Requested → FIS Approved
  • 11/12/2022
    FIS Approved → IA Signed
  • 03/08/2021
    Entered the queue with 406 MW, projected COD 07/31/2026
  • 03/08/2021
    Screening → FIS Requested