28INR0404 · Solar · Hill County
Penelope Solar
Penelope Solar is a 98 MW solar project in Hill County, Texas, connecting at New sub in the 234 Chatt - 3473 Ash Creek 138kV line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/24/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0404
- Capacity
- 98 MW
- Fuel
- Solar (PV)
- County
- Hill County
- Interconnecting entity
- Ash Creek Project LLC
- Projected COD
- 09/24/2029
- Entered queue
- 07/21/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/28/2026Screening → FIS Requested
- 07/21/2025Entered the queue with 98 MW, projected COD 09/24/2029
Other projects at this substation
No other projects at this substation.