ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0055 · Solar · Hill County

Three W Solar

Withdrawn

Three W Solar is a 111 MW solar project in Hill County, Texas, connecting at tap 138kV 3522 Hillboro1_8 - 237 Blanton CKT 1. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0055
Capacity
111 MW
Fuel
Solar (PV)
Interconnecting entity
Three W Solar LLC
Projected COD
09/04/2026
Entered queue
02/28/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Listed as withdrawn UNCONFIRMED
  • 03/19/2026
    Energization Approved → Sync Approved
  • 02/13/2026
    IA Signed → Energization Approved
  • 06/18/2025
    FIS Requested → FIS Approved
  • 03/28/2023
    FIS Approved → IA Signed
  • 02/28/2022
    Entered the queue with 111 MW, projected COD 09/04/2026
  • 02/28/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.