LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Hill County

LIBERTY 345 KV STATION (Bus# 68092)

1 active project totalling 1,400 MW is queued to connect at LIBERTY 345 KV STATION (Bus# 68092) in Hill County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,400 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
33INR0006Liberty Thermal Energy CenterGas1,400FIS Requested07/01/20320