Substation / point of interconnection ยท Hill County
68090 Sam Switch Bus 345kV
2 active projects totalling 1,028 MW are queued to connect at 68090 Sam Switch Bus 345kV in Hill County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,028 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0472 | Seven Angels Energy Storage I | BESS | 514 | FIS Requested | 12/31/2028 | 0 |
| 28INR0473 | Seven Angels Energy Storage II | BESS | 514 | FIS Requested | 12/31/2028 | 0 |