ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Hidalgo County power projects

Hidalgo County, Texas has 25 active power projects totalling 3,488 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,572 MW (74%). The largest single project is Anawa La Gas (250 MW natural gas). 5 projects have signed an interconnection agreement or reached a later stage. 5 projects in the county are listed as withdrawn or cancelled.

Active projects
25
3.5 GW capacity
IA signed or later
5
20% of active projects
Withdrawn or cancelled
5
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Hidalgo County

COD change
10/01/2026
Gunnar BESS · BESS · Hidalgo County
Projected COD moved 12/02/2026 → 11/25/2026. Moved earlier.
0 mo
MW change
10/01/2026
Anawa La Gas · Gas · Hidalgo County
Requested capacity reduced.
1,220 → 250 MW
Withdrawn
09/30/2026
Grapefruit Solar · Solar · Hidalgo County
Listed as inactive by ERCOT.
−291 MW
Stage change
09/08/2026
Gunnar BESS · BESS · Hidalgo County
Moved from Energization Approved to Sync Approved.
Sync Approved

All projects

ProjectFuelMWSubstationStageCOD
Anawa La GasGas250Liston 138 KV to Bates 138 KVFIS Requested12/30/2028
Monte Cristo II WindWind2348574 Pomelo 345kVIA Signed12/31/2028
Val Vista Grid BESS 2BESS211Tap 345kV 8383 North Edinburg - 80137 Stewart RoadIA Signed03/30/2029
Val Vista Grid BESS 1BESS209Tap 345kV 8383 North Edinburg - 80137 Stewart RoadIA Signed03/30/2029
McMEXICO STORAGEBESS2028644 Trade Zone 138kVFIS Requested11/30/2028
PSE Chihuahua TX StorageBESS200Tap 138kV 8392 Bates – 8394 ListonFIS Approved06/30/2028
Borderland ESCBESS200tap 138kV 8380 NEDIN4A – 8632 NMCALLEN4CFIS Requested11/30/2028
Eligius BESSBESS175tap 138kV Liston (#8394) – JL Bates (#8392) line, AEPFIS Requested11/28/2028
Sullivan SolarSolar171Tap 138kV 8798 La Grulla - 8355 GoodwinFIS Requested02/25/2029
Donna SolarSolar168Tap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01FIS Requested02/22/2029
Palladium StorageBESS156Tap 138 kV 8656 Luna - 8033 PanteraFIS Requested06/30/2028
Gunnar BESSBESS1558029 CLOSNER4A 138kVSync Approved11/25/2026
Hawkins BESSBESS15085005 ELGATO4A 138 kVFIS Requested01/16/2028
Anawa La BESSBESS104Tap 138KV 8394 Liston- 8392 BatesFIS Requested08/31/2027
Bronze Quinta StorageBESS104S_MCALLN 8371 (S. McAllen 138kV Substation)FIS Requested01/01/2028
Big Five StorageBESS102Tap 138kV (5784) Redgtss - (8380) NedinaFIS Requested01/15/2028
PSE Richardson TX StorageBESS100TAP 138KV 8374 SOUTH EAST EDINBURG - 8029 CLOSNERFIS Approved06/30/2028
Palmvalley StorageBESS100Frontera (#8980)FIS Requested05/01/2027
PSE Minnesota TX StorageBESS94Tap 138kV 8372 North Pharr – 8906 North AlamoFIS Requested06/30/2028
Anawa La SolarSolar93TAP 138 KV 8394 LISTON - 8392 BATESFIS Requested08/31/2027
Camellia StorageBESS91Tap 138 kV 8358FIS Requested06/30/2028
Billie StorageBESS84Tap 138kV 8357 North Weslaco – 8358 North MercedesScreening09/02/2029
Sullivan BESSBESS72Tap 138kV 8798 La Grulla - 8355 GoodwinFIS Requested02/25/2029
Donna BESSBESS54Tap 345 kV 80137 Stewart Road - 8383 North EdinburgFIS Requested02/22/2029
North Edinburg BESS 1BESS10North EdinburgSync Approved08/21/2026
Grapefruit SolarSolar291North Edinburg (Bus #8905) - Reforzar (Bus # 80078) 345kVWithdrawn12/31/2028
Citrus Grove Energy StorageBESS205Not listedWithdrawnn/a
Half Moon 2 BESSBESS102Not listedWithdrawnn/a
Wishbone Storage (SLF)BESS90Not listedWithdrawnn/a
Half Moon BatteryBESS30Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Hidalgo County?
ERCOT's October 2026 report lists 25 active projects in Hidalgo County totalling 3,488 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.