LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Hidalgo County

8574 Pomelo 345kV

1 active project totalling 234 MW is queued to connect at 8574 Pomelo 345kV in Hidalgo County, Texas, according to ERCOT's October 2026 report.

Active capacity
234 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
19INR0055Monte Cristo II WindWind234IA Signed12/31/20280