25INR0376 · BESS · Hidalgo County

Hawkins BESS

Hawkins BESS is a 150 MW battery storage project in Hidalgo County, Texas, connecting at 85005 ELGATO4A 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/16/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0376
Capacity
150 MW
Fuel
BESS (BA)
Interconnecting entity
BRP BLUE TOPAZ 7, LLC
Projected COD
01/16/2028
Entered queue
04/19/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/19/2023
    Entered the queue with 150 MW, projected COD 01/16/2028
  • 04/19/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.