25INR0376 · BESS · Hidalgo County
Hawkins BESS
Hawkins BESS is a 150 MW battery storage project in Hidalgo County, Texas, connecting at 85005 ELGATO4A 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/16/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0376
- Capacity
- 150 MW
- Fuel
- BESS (BA)
- Substation
- 85005 ELGATO4A 138 kV
- County
- Hidalgo County
- Interconnecting entity
- BRP BLUE TOPAZ 7, LLC
- Projected COD
- 01/16/2028
- Entered queue
- 04/19/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/19/2023Entered the queue with 150 MW, projected COD 01/16/2028
- 04/19/2023Screening → FIS Requested