23INR0480 · BESS · Hidalgo County
Camellia Storage
Camellia Storage is a 91 MW battery storage project in Hidalgo County, Texas, connecting at Tap 138 kV 8358. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0480
- Capacity
- 91 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138 kV 8358
- County
- Hidalgo County
- Interconnecting entity
- Camellia Storage Project LLC
- Projected COD
- 06/30/2028
- Entered queue
- 07/05/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/06/2022Screening → FIS Requested
- 07/05/2022Entered the queue with 91 MW, projected COD 06/30/2028
Other projects at this substation
No other projects at this substation.