LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Hidalgo County

Tap 138 kV 8656 Luna - 8033 Pantera

1 active project totalling 156 MW is queued to connect at Tap 138 kV 8656 Luna - 8033 Pantera in Hidalgo County, Texas, according to ERCOT's October 2026 report.

Active capacity
156 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0462Palladium StorageBESS156FIS Requested06/30/20280