Substation / point of interconnection ยท Hidalgo County
Tap 138 kV 8656 Luna - 8033 Pantera
1 active project totalling 156 MW is queued to connect at Tap 138 kV 8656 Luna - 8033 Pantera in Hidalgo County, Texas, according to ERCOT's October 2026 report.
Active capacity
156 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0462 | Palladium Storage | BESS | 156 | FIS Requested | 06/30/2028 | 0 |