LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0491 · BESS · Hidalgo County

Gunnar BESS

Gunnar BESS is a 155 MW battery storage project in Hidalgo County, Texas, connecting at 8029 CLOSNER4A 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/25/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0491
Capacity
155 MW
Fuel
BESS (BA)
Interconnecting entity
Gunnar Reliability Project LLC
Projected COD
11/25/2026
Entered queue
01/30/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/02/2026 → 11/25/2026 (0 months)
  • 09/08/2026
    Energization Approved → Sync Approved
  • 08/28/2026
    IA Signed → Energization Approved
  • 09/11/2025
    FIS Requested → FIS Approved
  • 09/22/2023
    FIS Approved → IA Signed
  • 01/30/2023
    Entered the queue with 155 MW, projected COD 12/02/2026
  • 01/30/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.