Substation / point of interconnection ยท Hidalgo County
8029 CLOSNER4A 138kV
1 active project totalling 155 MW is queued to connect at 8029 CLOSNER4A 138kV in Hidalgo County, Texas, according to ERCOT's October 2026 report.
Active capacity
155 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0491 | Gunnar BESS | BESS | 155 | Sync Approved | 11/25/2026 | 0 |