LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0039 · BESS · Hidalgo County

Borderland ESC

Borderland ESC is a 200 MW battery storage project in Hidalgo County, Texas, connecting at tap 138kV 8380 NEDIN4A – 8632 NMCALLEN4C. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0039
Capacity
200 MW
Fuel
BESS (BA)
Interconnecting entity
FRESH AIR ENERGY II, LLC
Projected COD
11/30/2028
Entered queue
02/08/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/08/2022
    Entered the queue with 200 MW, projected COD 11/30/2028
  • 02/08/2022
    Screening → FIS Requested