24INR0447 · BESS · Hidalgo County
PSE Chihuahua TX Storage
PSE Chihuahua TX Storage is a 200 MW battery storage project in Hidalgo County, Texas, connecting at Tap 138kV 8392 Bates – 8394 Liston. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 06/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0447
- Capacity
- 200 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV 8392 Bates – 8394 Liston
- County
- Hidalgo County
- Interconnecting entity
- PureSky Development Inc
- Projected COD
- 06/30/2028
- Entered queue
- 12/07/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/16/2025FIS Requested → FIS Approved
- 09/15/2023Screening → FIS Requested
- 12/07/2022Entered the queue with 200 MW, projected COD 06/30/2028
Other projects at this substation