Ector County power projects

Ector County, Texas has 21 active power projects totalling 4,055 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,523 MW (62%). The largest single project is Gypsum Plains Solar (503 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
21
4.1 GW capacity
IA signed or later
4
19% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Ector County

COD change
10/01/2026
Apple BESS · BESS · Ector County
Projected COD moved 10/05/2026 → 11/27/2026. Delay #1 for this project.
+2 mo
Withdrawn
09/03/2026
EMPower Odessa (TEF - Due Diligence) · Gas · Ector County
Listed as cancelled by ERCOT.
−123 MW

All projects

ProjectFuelMWSubstationStageCOD
Gypsum Plains SolarSolar503Tap 345kv line Wolf BUS# 11010 - Reiter BUS#18544FIS Requested06/21/2029
Jackrabbit Flats SolarSolar401Tap 345 kV 1185 Midland County NW - 1018 MossFIS Requested06/29/2030
Greyhound SolarSolar335Tap 345kV 11010 Wolf - 1018 MossSync Approved06/30/2026
Van Zandt Energy StorageBESS2561027 Odessa EHV Switch 138 kVIA Signed05/15/2027
Velociraptor BESS IIBESS246Tap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KVFIS Requested12/01/2029
Velociraptor BESS IBESS246#10012 METEOR 5 Substation 345kVFIS Requested12/01/2029
Velociraptor Solar IISolar242Tap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KVFIS Requested12/01/2029
Velociraptor Solar ISolar242#10012 METEOR 5 Substation 345kVFIS Requested12/01/2029
Gypsum Plains StorageBESS211Tap 345kv 11010 Wolf - 18544 ReiterFIS Requested06/21/2029
Sisters Solar IISolar206tap 345kV 11010 Wolf Switching Station - 10012 MeteorFIS Approved12/15/2028
Sisters Solar - Phase 2Solar20210009 McGee 345 kVFIS Requested09/23/2028
Seragio BESSBESS20111140 ECTRCNTYN_8 138kVFIS Approved04/30/2028
GPlains SolarSolar151Tap 138kV #1013 WOLFSS_8 - #1103 SANDHLTA_8FIS Requested06/21/2029
Momentum Hazy Jane BESSBESS126Tap 138kV 1102 Judkins - 1110 EdwardFIS Requested02/26/2028
Ophelia SolarSolar110Tap 138 kV Raceway Switch #18663 - Shin Oak POD #11128FIS Requested09/19/2028
Firebird BESSBESS103Tap 138kV #1099 Southwestern Portland Tap - #1052 RexallFIS Requested06/29/2029
Sisters SolarSolar100tapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf Switching Station (Bus# 11010)IA Signed09/23/2028
M-Bar BESS IBESS821141 Holt Switch Substation 138 kVFIS Requested09/18/2028
GPlains StorageBESS51Tap 138kV WOLFSS_8 (1013) - SANDHLTA_8 (1103)FIS Requested06/21/2029
M-Bar Solar ISolar301141 Holt Switch Substation 138kVFIS Approved09/18/2028
Apple BESSBESS10AppleEnergization Approved11/27/2026
Sunlight SolarSolar203Not listedWithdrawnn/a
EMPower Odessa (TEF - Due Diligence)Gas123Tap 138 kV 1110 EDWARDS TAP - 1102 JUDKINSWithdrawn03/09/2028
Firebird SolarSolar100Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Ector County?
ERCOT's October 2026 report lists 21 active projects in Ector County totalling 4,055 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.