ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0322 · Solar · Ector County

Velociraptor Solar II

Velociraptor Solar II is a 242 MW solar project in Ector County, Texas, connecting at Tap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0322
Capacity
242 MW
Fuel
Solar (PV)
Interconnecting entity
Velociraptor Solar II, LLC
Projected COD
12/01/2029
Entered queue
05/12/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/12/2025
    Entered the queue with 242 MW, projected COD 12/01/2029
  • 05/12/2025
    Screening → FIS Requested

Other projects at this substation

Velociraptor BESS IIBESS246 MWFIS Requested