28INR0323 · BESS · Ector County

Velociraptor BESS II

Velociraptor BESS II is a 246 MW battery storage project in Ector County, Texas, connecting at Tap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0323
Capacity
246 MW
Fuel
BESS (BA)
Interconnecting entity
Velociraptor BESS II, LLC
Projected COD
12/01/2029
Entered queue
05/07/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/07/2025
    Entered the queue with 246 MW, projected COD 12/01/2029
  • 05/07/2025
    Screening → FIS Requested

Other projects at this substation

Velociraptor Solar IISolar242 MWFIS Requested