LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Ector County

#10012 METEOR 5 Substation 345kV

2 active projects totalling 488 MW are queued to connect at #10012 METEOR 5 Substation 345kV in Ector County, Texas, according to ERCOT's October 2026 report.

Active capacity
488 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0493Velociraptor BESS IBESS246FIS Requested12/01/20290
22INR0218Velociraptor Solar ISolar242FIS Requested12/01/20290