28INR0228 · BESS · Ector County
GPlains Storage
GPlains Storage is a 51 MW battery storage project in Ector County, Texas, connecting at Tap 138kV WOLFSS_8 (1013) - SANDHLTA_8 (1103). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/21/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0228
- Capacity
- 51 MW
- Fuel
- BESS (BA)
- County
- Ector County
- Interconnecting entity
- Gypsum Plains Solar, LLC
- Projected COD
- 06/21/2029
- Entered queue
- 04/11/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/11/2025Entered the queue with 51 MW, projected COD 06/21/2029
- 04/11/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.