28INR0177 · Solar · Ector County
Sisters Solar II
Sisters Solar II is a 206 MW solar project in Ector County, Texas, connecting at tap 345kV 11010 Wolf Switching Station - 10012 Meteor. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0177
- Capacity
- 206 MW
- Fuel
- Solar (PV)
- County
- Ector County
- Interconnecting entity
- Oberon Solar III, LLC
- Projected COD
- 12/15/2028
- Entered queue
- 10/18/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/27/2026FIS Requested → FIS Approved
- 10/18/2024Entered the queue with 206 MW, projected COD 12/15/2028
- 10/18/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.