26INR0287 · BESS · Ector County
Firebird BESS
Firebird BESS is a 103 MW battery storage project in Ector County, Texas, connecting at Tap 138kV #1099 Southwestern Portland Tap - #1052 Rexall. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/29/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0287
- Capacity
- 103 MW
- Fuel
- BESS (BA)
- County
- Ector County
- Interconnecting entity
- TX BESS 6, LLC
- Projected COD
- 06/29/2029
- Entered queue
- 10/31/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/31/2023Entered the queue with 103 MW, projected COD 06/29/2029
- 10/31/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.