LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Ector County

Tap 345kV 11010 Wolf - 1018 Moss

1 active project totalling 335 MW is queued to connect at Tap 345kV 11010 Wolf - 1018 Moss in Ector County, Texas, according to ERCOT's October 2026 report.

Active capacity
335 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
21INR0268Greyhound SolarSolar335Sync Approved06/30/20260