EMPower Odessa (TEF - Due Diligence) is a 123 MW natural gas project in Ector County, Texas, connecting at Tap 138 kV 1110 EDWARDS TAP - 1102 JUDKINS. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0272
Capacity
123 MW
Fuel
Gas (IC)
Interconnecting entity
EMPOWER USA, LLC
Projected COD
03/09/2028
Entered queue
07/03/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/03/2026
    Listed as cancelled
  • 03/13/2026
    FIS Requested → IA Signed
  • 07/03/2024
    Entered the queue with 123 MW, projected COD 03/09/2028
  • 07/03/2024
    Screening → FIS Requested