LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Colorado County power projects

Colorado County, Texas has 14 active power projects totalling 1,784 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,268 MW (71%). The largest single project is Altair Energy Storage (202 MW battery storage). 4 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
14
1.8 GW capacity
IA signed or later
4
29% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Colorado County

COD change
10/01/2026
Kleimann BESS · BESS · Colorado County
Projected COD moved 11/30/2026 → 12/08/2026. Delay #1 for this project.
0 mo
Withdrawn
09/14/2026
Pearl Crescent Solar · Solar · Colorado County
Listed as cancelled by ERCOT.
−208 MW
Withdrawn
09/14/2026
Pearl Crescent Storage · BESS · Colorado County
Listed as cancelled by ERCOT.
−50 MW

All projects

ProjectFuelMWSubstationStageCOD
Altair Energy StorageBESS202Tap on 138 kV ALTAIR (bus# 78118) to STAFFORD HILL (bus# 78520)FIS Requested03/31/2030
Moonlight Sonata BESSBESS201Altair (78118) – Nada (78103) 138KVFIS Requested07/01/2028
Cottontail Energy CenterBESS2017258 Glidden Substation 138kVFIS Requested10/19/2027
Paloma Energy CenterSolar194Tap 138 kV 57640 Rock Island - 57639 SheridanFIS Requested12/31/2027
Montezuma StorageBESS184L_GLIDDE8_1Y; Bus number - 7258 138KVFIS Requested10/16/2030
Firefly Fields StorageBESS156Tap 138 kV 57640 Rock Island to 7258 GliddenFIS Requested09/30/2028
Driet BESSBESS1507254 WEIMAR8 138kVIA Signed06/20/2028
Rock Island Generating (TEF -Due Diligence)Gas12257640 Rock Island 138 kVIA Signed06/01/2027
Firefly Fields SolarSolar100Tap 138 kV 57640 Rock Island - 7258 GliddenFIS Requested09/30/2028
Radiant Plains Energy Center BESSBESS100Tap 138-kV Weimar (7254) to Schulenburg (7252)Screening12/27/2029
Radiant Plains Energy Center SolarSolar100Tap 138-kV Weimar (7254) to Schulenburg (7252)Screening12/27/2029
Paloma Energy Center BESSBESS54Tap 138kV 57640 Rock Island - 57639 SheridanFIS Requested12/31/2027
Stafford Hill BESSBESS10New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Stafford Hill TSP Station Code: STAFHI Load Name: LOAD1 Bus #: PTI Bus Number: 78520 Voltage (Transmission level kV): 138kV Node (load/load XFMR in NMMS), Tranformer: LD01IA Signed11/14/2026
Kleimann BESSBESS10New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Kleimann TSP Station Code: KLEIMA Load Name: LOAD1 Bus #: PTI Bus Number: 78115 Voltage (Transmission level kV): 138kV Node (load/load XFMR in NMMS), Tranformer: LD01IA Signed12/08/2026
Pearl Crescent SolarSolar208Rock Island (57640) 138kVWithdrawn12/08/2026
Pearl Crescent StorageBESS50Rock Island (57640) 138kVWithdrawn12/15/2026

For residents and landowners

What power projects are planned in Colorado County?
ERCOT's October 2026 report lists 14 active projects in Colorado County totalling 1,784 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.