25INR0402 · BESS · Colorado County
Driet BESS
Driet BESS is a 150 MW battery storage project in Colorado County, Texas, connecting at 7254 WEIMAR8 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/20/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0402
- Capacity
- 150 MW
- Fuel
- BESS (BA)
- Substation
- 7254 WEIMAR8 138kV
- County
- Colorado County
- Interconnecting entity
- Driet BESS LLC
- Projected COD
- 06/20/2028
- Entered queue
- 05/31/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/23/2025FIS Requested → IA Signed
- 05/31/2023Entered the queue with 150 MW, projected COD 06/20/2028
- 05/31/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.