1 active project totalling 150 MW is queued to connect at 7254 WEIMAR8 138kV in Colorado County, Texas, according to ERCOT's October 2026 report.
Active capacity
150 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0402 | Driet BESS | BESS | 150 | IA Signed | 06/20/2028 | 0 |