Cottontail Energy Center

Cottontail Energy Center is a 201 MW battery storage project in Colorado County, Texas, connecting at 7258 Glidden Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/19/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0259
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Cottontail Energy Center, LLC
Projected COD
10/19/2027
Entered queue
10/17/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/17/2023
    Entered the queue with 201 MW, projected COD 10/19/2027
  • 10/17/2023
    Screening → FIS Requested