32INR0002 · Solar · Colorado County
Radiant Plains Energy Center Solar
Radiant Plains Energy Center Solar is a 100 MW solar project in Colorado County, Texas, connecting at Tap 138-kV Weimar (7254) to Schulenburg (7252). ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 12/27/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 32INR0002
- Capacity
- 100 MW
- Fuel
- Solar (PV)
- County
- Colorado County
- Interconnecting entity
- Adapture Solar Development
- Projected COD
- 12/27/2029
- Entered queue
- 06/12/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/12/2025Entered the queue with 100 MW, projected COD 12/27/2029
Other projects at this substation
| Radiant Plains Energy Center BESS | BESS | 100 MW | Screening |