LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
32INR0002 · Solar · Colorado County

Radiant Plains Energy Center Solar

Radiant Plains Energy Center Solar is a 100 MW solar project in Colorado County, Texas, connecting at Tap 138-kV Weimar (7254) to Schulenburg (7252). ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 12/27/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
32INR0002
Capacity
100 MW
Fuel
Solar (PV)
Interconnecting entity
Adapture Solar Development
Projected COD
12/27/2029
Entered queue
06/12/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/12/2025
    Entered the queue with 100 MW, projected COD 12/27/2029

Other projects at this substation