Pearl Crescent Solar is a 208 MW solar project in Colorado County, Texas, connecting at Rock Island (57640) 138kV. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0349
- Capacity
- 208 MW
- Fuel
- Solar (PV)
- Substation
- Rock Island (57640) 138kV
- County
- Colorado County
- Interconnecting entity
- RWE Solar Development, LLC
- Projected COD
- 12/08/2026
- Entered queue
- 05/31/2019
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/14/2026Listed as cancelled
- 09/30/2019Screening → FIS Requested
- 05/31/2019Entered the queue with 208 MW, projected COD 12/08/2026
Other projects at this substation
| Pearl Crescent Storage | BESS | 50 MW | Withdrawn |