LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0085 · Solar · Colorado County

Firefly Fields Solar

Firefly Fields Solar is a 100 MW solar project in Colorado County, Texas, connecting at Tap 138 kV 57640 Rock Island - 7258 Glidden. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0085
Capacity
100 MW
Fuel
Solar (PV)
Interconnecting entity
Firefly Fields Energy Center LLC
Projected COD
09/30/2028
Entered queue
12/09/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/09/2024
    Entered the queue with 100 MW, projected COD 09/30/2028
  • 12/09/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.