25INR0769 · BESS · Colorado County

Kleimann BESS

COD delayed 1×

Kleimann BESS is a 9.9 MW battery storage project in Colorado County, Texas, connecting at New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Kleimann TSP Station Code: KLEIMA Load Name: LOAD1 Bus #: PTI Bus Number: 78115 Voltage (Transmission level kV): 138kV Node (load/load XFMR in NMMS), Tranformer: LD01. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/08/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0769
Capacity
9.9 MW
Fuel
BESS (BA)
Interconnecting entity
Columbus Clean Energy Center, LLC
Projected COD
12/08/2026
Entered queue
03/31/2025
ERCOT zone
SOUTH
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 11/30/2026 → 12/08/2026 (0 months)
  • 03/31/2025
    Entered the queue with 9.9 MW, projected COD 11/30/2026
  • 03/31/2025
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.