Zapata County power projects

Zapata County, Texas has 27 active power projects totalling 6,291 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,283 MW (36%). The largest single project is Falcon BESS (517 MW battery storage). 5 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
27
6.3 GW capacity
IA signed or later
5
19% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Zapata County

COD change
10/01/2026
Slate Solar Project · Solar · Zapata County
Projected COD moved 10/30/2027 → 01/15/2030. Delay #1 for this project.
+27 mo

All projects

ProjectFuelMWSubstationStageCOD
Falcon BESSBESS517Tap 345kV #80225 CENIZO to #80307 DEL SOLFIS Requested12/01/2029
Falcon SolarSolar502Tap 345kV #80225 Cenizo7C to #80307 Del Sol7CScreening12/01/2029
Freedom Falcon BESSBESS502Tap 345kV #80224 Tiempo - #80227 RapidoFIS Requested08/11/2028
Vaquero 1 WindWind400tap 345kV 8905 N Edinb - 8455 Lon HillFIS Requested01/15/2027
Tetris SolarSolar359TAP 345kV 80307 Del Sol 7C - 80225 Cenizo 7CFIS Requested07/01/2029
Sierra Madre SolarSolar255tap 345kV 80307 Del Sol - 80225 CenizoFIS Requested12/01/2027
Rancho Grande SolarSolar252345 kV Tiempo Substation #80224FIS Requested05/09/2028
La Morena Energy Center BESSBESS250Tap 345 kV 80225 CENIZO7C - 80307 DELSOL7CScreening05/07/2029
La Morena Energy Center SolarSolar250Tap 345 kV 80225 CENIZO7C - 80307 DELSOL7CScreening05/07/2029
Wallflower Energy StorageBESS209Tap the 345 kV Cenizo (#80225) - Del Sol (#80307) line.FIS Requested12/30/2029
Wallflower SolarSolar201Tap the 345 kV Cenizo (#80225) - Del Sol (#80307) line.FIS Requested12/30/2029
Zelus BESSBESS201the 138 kV Zapata Substation (#8299; AEP)FIS Requested12/01/2027
Falcon Zapata Storage 138BESS201Tap 138kV 8299 Zapata - 8957 LopenoIA Signed03/11/2028
Cascabel Wind 2Wind198345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307).IA Signed12/01/2027
Cascabel Wind 1Wind198345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307).IA Signed12/01/2027
Barrosos Creek Wind 3Wind198#80227 Rapido 345 kVFIS Requested05/31/2028
Barrosos Creek Wind 4Wind198#80227 Rapido 345 kVFIS Requested05/31/2028
Corralitos Wind 1Wind196Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation)IA Signed12/01/2027
Corralitos Wind 3Wind196ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C - 80307 DELSOL7C)FIS Requested05/31/2028
Corralitos Wind 2Wind195Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation)IA Signed12/31/2027
Corralitos Wind 4Wind195ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C - 80307 DELSOL7C)FIS Requested05/31/2028
Quarter Ranch SolarSolar15480223 Cenizo Substation 345kVFIS Requested10/15/2028
Slate Solar ProjectSolar105Tap 138kV 8646 Rio Bravo - 8985 San YgancioFIS Requested01/15/2030
Big River SolarSolar104tap 138kV 8299 Zapata - 8957 Lopeno4AFIS Requested12/31/2028
Falcon II BESSBESS1038004 Revilla 138 kVFIS Requested02/16/2032
Falcon II SolarSolar1008004 Revilla 138 kVFIS Requested02/16/2032
Big River BESSBESS51tap 138kV 8299 Zapata - 8957 Lopeno4AFIS Requested12/31/2028
Tetris Solar (Alternative POI)Solar359Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Zapata County?
ERCOT's October 2026 report lists 27 active projects in Zapata County totalling 6,291 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.