LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Zapata County

8004 Revilla 138 kV

2 active projects totalling 204 MW are queued to connect at 8004 Revilla 138 kV in Zapata County, Texas, according to ERCOT's October 2026 report.

Active capacity
204 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0483Falcon II BESSBESS103FIS Requested02/16/20320
28INR0482Falcon II SolarSolar100FIS Requested02/16/20320