Falcon II Solar is a 100 MW solar project in Zapata County, Texas, connecting at 8004 Revilla 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/16/2032.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0482
- Capacity
- 100 MW
- Fuel
- Solar (PV)
- Substation
- 8004 Revilla 138 kV
- County
- Zapata County
- Interconnecting entity
- Falcon Energy Project
- Projected COD
- 02/16/2032
- Entered queue
- 03/20/2026
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/20/2026Entered the queue with 100 MW, projected COD 02/16/2032
- 03/20/2026Screening → FIS Requested
Other projects at this substation
| Falcon II BESS | BESS | 103 MW | FIS Requested |