ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0340 · Wind · Zapata County

Corralitos Wind 4

Corralitos Wind 4 is a 195 MW wind project in Zapata County, Texas, connecting at ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C - 80307 DELSOL7C). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0340
Capacity
195 MW
Fuel
Wind (WT)
Interconnecting entity
Las Crestas Wind Energy, LLC
Projected COD
05/31/2028
Entered queue
06/13/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/24/2025
    Screening → FIS Requested
  • 06/13/2025
    Entered the queue with 195 MW, projected COD 05/31/2028

Other projects at this substation

Corralitos Wind 3Wind196 MWFIS Requested