LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Zapata County

tap 138kV 8299 Zapata - 8957 Lopeno4A

2 active projects totalling 156 MW are queued to connect at tap 138kV 8299 Zapata - 8957 Lopeno4A in Zapata County, Texas, according to ERCOT's October 2026 report.

Active capacity
156 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0215Big River SolarSolar104FIS Requested12/31/20280
23INR0237Big River BESSBESS51FIS Requested12/31/20280