23INR0215 · Solar · Zapata County
Big River Solar
Big River Solar is a 104 MW solar project in Zapata County, Texas, connecting at tap 138kV 8299 Zapata - 8957 Lopeno4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0215
- Capacity
- 104 MW
- Fuel
- Solar (PV)
- Substation
- tap 138kV 8299 Zapata - 8957 Lopeno4A
- County
- Zapata County
- Interconnecting entity
- Rio Grande River Solar LLC
- Projected COD
- 12/31/2028
- Entered queue
- 04/15/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/15/2021Entered the queue with 104 MW, projected COD 12/31/2028
- 04/15/2021Screening → FIS Requested
Other projects at this substation
| Big River BESS | BESS | 51 MW | FIS Requested |