LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0503 · Solar · Zapata County

Rancho Grande Solar

Rancho Grande Solar is a 252 MW solar project in Zapata County, Texas, connecting at 345 kV Tiempo Substation #80224. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/09/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0503
Capacity
252 MW
Fuel
Solar (PV)
Interconnecting entity
Bordas Renewable Energy, LLC
Projected COD
05/09/2028
Entered queue
03/27/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/27/2026
    Entered the queue with 252 MW, projected COD 05/09/2028
  • 03/27/2026
    Screening → FIS Requested