ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Borden County power projects

Borden County, Texas has 17 active power projects totalling 5,257 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 3,852 MW (73%). The largest single project is Magnet Solar (503 MW solar). 9 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
17
5.3 GW capacity
IA signed or later
9
53% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Borden County

COD change
10/01/2026
Magnet Solar · Solar · Borden County
Projected COD moved 10/06/2028 → 09/29/2029. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Magnet Storage · BESS · Borden County
Projected COD moved 07/15/2029 → 09/29/2029. Delay #1 for this project.
+2 mo
Stage change
09/15/2026
Caesar Storage · BESS · Borden County
Moved from FIS Requested to IA Signed.
IA Signed
Stage change
09/15/2026
Caesar Solar · Solar · Borden County
Moved from FIS Requested to IA Signed.
IA Signed

All projects

ProjectFuelMWSubstationStageCOD
Magnet SolarSolar503Faraday Substation 345kV - Bus #59905IA Signed09/29/2029
Juno 3 SolarSolar500#59916 Buck Canyon 345kVIA Signed11/30/2027
Lyra StorageBESS500345kV MULESHOE (#59922)IA Signed11/12/2026
Lyra SolarSolar500345kV MULESHOE (#59922)IA Signed09/15/2027
Draco SolarSolar500Tap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2FIS Requested08/19/2027
Antila SolarSolar500#59916 Buck Canyon 345kVIA Signed11/30/2027
Enfinity Post Oak Solar SLFSolar500345kV MULESHOE (#59922)FIS Requested12/18/2029
Magnet StorageBESS427Faraday 345 kV Substation (#59905)FIS Requested09/29/2029
Uva Creek SolarSolar302Muleshoe #59922 345 KVIA Signed08/25/2028
Gail Mountain SolarSolar244Muleshoe (Bus #59922) 345 kVIA Signed08/25/2028
Caesar StorageBESS20659916 Buck Canyon 345 kVIA Signed11/26/2029
Enfinity White Oak BESSBESS200Tap 138kV Key (1307) to 138kV Gail (1308)FIS Requested09/17/2029
Caesar SolarSolar18259916 Buck Canyon 345 kVIA Signed11/26/2029
Borden Dino SolarSolar12059905 FARADAY 345KVFIS Requested07/01/2028
Borden Dino BESSBESS6059905 FARADAY 345KVFIS Requested07/01/2028
Stephens Ranch Wind RepowerWind1259900 Long Draw 345 kVFIS Requested11/01/2027
Enfinity Post Oak Storage SLFBESS0345kV MULESHOE (#59922)FIS Requested12/18/2029
Tumbleweed SolarSolar614Not listedWithdrawnn/a
Tumbleweed StorageBESS507Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Borden County?
ERCOT's October 2026 report lists 17 active projects in Borden County totalling 5,257 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.