29INR0292 · BESS · Borden County

Enfinity Post Oak Storage SLF

Enfinity Post Oak Storage SLF is a 0 MW battery storage project in Borden County, Texas, connecting at 345kV MULESHOE (#59922). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/18/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0292
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
EG White Oak LLC
Projected COD
12/18/2029
Entered queue
03/27/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/27/2026
    Entered the queue with 0 MW, projected COD 12/18/2029
  • 03/27/2026
    Screening → FIS Requested

Other projects at this substation

Lyra StorageBESS500 MWIA Signed
Lyra SolarSolar500 MWIA Signed
Enfinity Post Oak Solar SLFSolar500 MWFIS Requested