LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0291 · Solar · Borden County

Enfinity Post Oak Solar SLF

Enfinity Post Oak Solar SLF is a 500 MW solar project in Borden County, Texas, connecting at 345kV MULESHOE (#59922). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/18/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0291
Capacity
500 MW
Fuel
Solar (PV)
Interconnecting entity
EG White Oak LLC
Projected COD
12/18/2029
Entered queue
03/27/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/27/2026
    Entered the queue with 500 MW, projected COD 12/18/2029
  • 03/27/2026
    Screening → FIS Requested

Other projects at this substation

Lyra StorageBESS500 MWIA Signed
Lyra SolarSolar500 MWIA Signed
Enfinity Post Oak Storage SLFBESS0 MWFIS Requested