27INR0434 · Solar · Borden County
Lyra Solar
Lyra Solar is a 500 MW solar project in Borden County, Texas, connecting at 345kV MULESHOE (#59922). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0434
- Capacity
- 500 MW
- Fuel
- Solar (PV)
- Substation
- 345kV MULESHOE (#59922)
- County
- Borden County
- Interconnecting entity
- Juno Solar 4
- Projected COD
- 09/15/2027
- Entered queue
- 03/20/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/01/2025FIS Requested → IA Signed
- 03/20/2025Entered the queue with 500 MW, projected COD 09/15/2027
- 03/20/2025Screening → FIS Requested
Other projects at this substation
| Lyra Storage | BESS | 500 MW | IA Signed |
| Enfinity Post Oak Solar SLF | Solar | 500 MW | FIS Requested |
| Enfinity Post Oak Storage SLF | BESS | 0 MW | FIS Requested |