ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0298 · BESS · Borden County

Magnet Storage

COD delayed 1×

Magnet Storage is a 427 MW battery storage project in Borden County, Texas, connecting at Faraday 345 kV Substation (#59905). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/29/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0298
Capacity
427 MW
Fuel
BESS (BA)
Interconnecting entity
HyFuels Big Spring LLC
Projected COD
09/29/2029
Entered queue
07/29/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 07/15/2029 → 09/29/2029 (+2 months)
  • 08/22/2025
    Screening → FIS Requested
  • 07/29/2025
    Entered the queue with 427 MW, projected COD 07/15/2029

Other projects at this substation

No other projects at this substation.