28INR0298 · BESS · Borden County
Magnet Storage
COD delayed 1×
Magnet Storage is a 427 MW battery storage project in Borden County, Texas, connecting at Faraday 345 kV Substation (#59905). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/29/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0298
- Capacity
- 427 MW
- Fuel
- BESS (BA)
- Substation
- Faraday 345 kV Substation (#59905)
- County
- Borden County
- Interconnecting entity
- HyFuels Big Spring LLC
- Projected COD
- 09/29/2029
- Entered queue
- 07/29/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 07/15/2029 → 09/29/2029 (+2 months)
- 08/22/2025Screening → FIS Requested
- 07/29/2025Entered the queue with 427 MW, projected COD 07/15/2029
Other projects at this substation
No other projects at this substation.