ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0621 · Solar · Borden County

Juno 3 Solar

Juno 3 Solar is a 500 MW solar project in Borden County, Texas, connecting at #59916 Buck Canyon 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/30/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0621
Capacity
500 MW
Fuel
Solar (PV)
Interconnecting entity
Juno Solar 3
Projected COD
11/30/2027
Entered queue
03/18/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/01/2025
    FIS Requested → IA Signed
  • 03/18/2025
    Entered the queue with 500 MW, projected COD 11/30/2027
  • 03/18/2025
    Screening → FIS Requested

Other projects at this substation

Antila SolarSolar500 MWIA Signed