LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0297 · Solar · Borden County

Magnet Solar

COD delayed 1×

Magnet Solar is a 503 MW solar project in Borden County, Texas, connecting at Faraday Substation 345kV - Bus #59905. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/29/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0297
Capacity
503 MW
Fuel
Solar (PV)
Interconnecting entity
HyFuels Big Spring Solar LLC
Projected COD
09/29/2029
Entered queue
04/21/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/06/2028 → 09/29/2029 (+12 months)
  • 12/11/2025
    FIS Requested → IA Signed
  • 04/24/2025
    Screening → FIS Requested
  • 04/21/2025
    Entered the queue with 503 MW, projected COD 10/06/2028

Other projects at this substation

No other projects at this substation.