Bexar County power projects
Bexar County, Texas has 23 active power projects totalling 5,170 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 4,983 MW (96%). The largest single project is Howard Road BESS (618 MW battery storage). 10 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
23
5.2 GW capacity
IA signed or later
10
43% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in Bexar County
COD change
10/01/2026
CPS Energy AvR1CT2 Rotor Replacement · Gas · Bexar County
Projected COD moved 08/07/2026 → 08/14/2026. Delay #1 for this project.
0 mo
COD change
10/01/2026
CPS AvR CT1 Rotor Replacement · Gas · Bexar County
Projected COD moved 08/07/2026 → 08/14/2026. Delay #1 for this project.
0 mo
COD change
10/01/2026
Bexar Martinez BESS · BESS · Bexar County
Projected COD moved 01/06/2027 → 01/23/2027. Delay #1 for this project.
+1 mo
Stage change
09/15/2026
Energization Approved
All projects
For residents and landowners
- What power projects are planned in Bexar County?
- ERCOT's October 2026 report lists 23 active projects in Bexar County totalling 5,170 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.