23INR0467 · BESS · Bexar County

Lavender Storage Project

Lavender Storage Project is a 232 MW battery storage project in Bexar County, Texas, connecting at Tap 138kV Deely (bus 5110) - Laredo (bus 5255). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/13/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0467
Capacity
232 MW
Fuel
BESS (BA)
Interconnecting entity
Lavender Storage Project LLC
Projected COD
09/13/2029
Entered queue
02/28/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/23/2025
    FIS Requested → IA Signed
  • 10/21/2022
    Screening → FIS Requested
  • 02/28/2022
    Entered the queue with 232 MW, projected COD 09/13/2029

Other projects at this substation

No other projects at this substation.