ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0702 · BESS · Bexar County

Bexar Martinez BESS

COD delayed 1×

Bexar Martinez BESS is a 10 MW battery storage project in Bexar County, Texas, connecting at Martinez. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 01/23/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0702
Capacity
10 MW
Fuel
BESS (BA)
Substation
Martinez
Interconnecting entity
Bexar Martinez LLC
Projected COD
01/23/2027
Entered queue
02/03/2026
ERCOT zone
SOUTH
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 01/06/2027 → 01/23/2027 (+1 months)
  • 09/15/2026
    IA Signed → Energization Approved
  • 02/03/2026
    Entered the queue with 10 MW, projected COD 01/06/2027
  • 02/03/2026
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.