26INR0702 · BESS · Bexar County
Bexar Martinez BESS
COD delayed 1×
Bexar Martinez BESS is a 10 MW battery storage project in Bexar County, Texas, connecting at Martinez. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 01/23/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0702
- Capacity
- 10 MW
- Fuel
- BESS (BA)
- Substation
- Martinez
- County
- Bexar County
- Interconnecting entity
- Bexar Martinez LLC
- Projected COD
- 01/23/2027
- Entered queue
- 02/03/2026
- ERCOT zone
- SOUTH
- Size category
- Small
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 01/06/2027 → 01/23/2027 (+1 months)
- 09/15/2026IA Signed → Energization Approved
- 02/03/2026Entered the queue with 10 MW, projected COD 01/06/2027
- 02/03/2026Screening → IA Signed
Other projects at this substation
No other projects at this substation.